The Office Move Checklist: Planning a Commercial Move That Doesn’t Stop Work
Residential moves are measured in hours; office moves are measured in downtime. Every decision below exists to protect one thing — the business opening on Monday.
Key Takeaways
-
Order the internet circuit at least 8 weeks before the move: Comcast’s best stated case for one dedicated product is 30 days.
-
One Atlanta tower’s 2022 manual puts moves on weekends or weekday evenings, booked two weeks ahead, with the mover’s COI in five days ahead.
-
The FCC’s one-business-day porting rule covers simple ports, generally a single line, not a whole office.
-
A Georgia office move also means IRS Form 8822-B, a Secretary of State update and, in Atlanta, a $50 zoning review.
8 weeks out Lock the constraints
Eight weeks out, lock the things you cannot rush: one decision-maker, building rules and the internet order.
-
One coordinator with authority — a single decision-maker for the mover, both landlords, and IT.
-
Both buildings’ rules in writing: COI limits and named insureds, dock hours, freight elevator reservations, protection requirements (masonite, corner guards), after-hours-only windows. The 2022 tenant manual for 1180 Peachtree puts moves on weekends or after 5 p.m. (6 p.m. in another section), scheduled two weeks ahead, plus a mover’s COI (proof of insurance) 5 days ahead. LIOO issues COIs free, the same day it receives the requirements.
-
Order the internet circuit now, or at lease signing. No carrier page we found gives a typical install time: Comcast Business says as short as 30 days for one dedicated product, and Verizon’s order manager sets the due dates after signing.
-
Inventory triage: what moves, what’s replaced, what’s decommissioned or donated — moving furniture nobody wants is money wasted. Before donating computers, delete all personal information (NIST SP 800-88 is the federal guide).
-
Book the mover with a walkthrough of both sites — zone maps, crew size, and the after-hours window set the quote. That’s the standard commercial moving scoping process. LIOO uses its standard hourly rate card, at the same rates on nights and weekends.
4 weeks out IT drives the date
Four weeks out, IT turns the internet order into a cutover plan.
-
Internet install at the new suite — confirm the date in writing, test the line before move weekend, and keep the old account open until the new one works.
-
Cutover plan: who disconnects, what’s imaged/backed up, how servers and network gear travel (padded, upright, chain-of-custody), who reconnects and tests.
-
Phone numbers: the FCC says you can keep your numbers when you change providers in the same area. Its one-business-day rule covers simple ports, generally a single line, so allow longer, and keep the old service active until the port is done.
-
New-space plan taped to the wall: a zone map (A/B/C…) with every desk, office, and room numbered — crews deliver to labels, not to memory.
2 weeks out People & packing
Two weeks out, the work shifts to people: who packs what, and who needs the new address.
-
Employees pack their own desks into labeled boxes (zone + name) with a hard deadline the day before the move; common areas get packing crew hours.
-
Furniture teardown scheduled — cubicles and conference tables come apart before truck day, hardware bagged per unit.
-
Update the world: address on Google, invoices, vendors, mail forwarding, building directories.
Office move weekend The zone-map run
On move weekend, the crew works the zone map while IT handles the cutover.
-
Friday close: IT disconnects and stages; boxes staged by zone.
-
The move: building protection down, freight elevator window used end-to-end, everything delivered to its zone label.
-
Sunday: IT reconnects and tests; punch-list walk of both suites (damage, leftovers, keys/badges).
-
Monday: open. The empty-suite walkthrough with photos closes the old lease cleanly.
What order should IT cut over in an office move?
A common office IT cutover order is network first, then servers, then desks. Sysadmins in two Spiceworks threads disagree on details, but a desk can’t work until the services beneath it do.
-
Before the weekend: test-restore your backups and make any network changes now, not during the move.
-
Friday: shut down desks, then servers, leaving domain controllers and DHCP and DNS servers for last.
-
Sunday: confirm the internet and firewall, start those core servers first, then phones and desks, and test from a real desk.
-
Who carries what: put it in writing. LIOO’s included released valuation is $0.60 per pound per item, capped at $2,000 per move, and is not insurance, so ask your business insurer about servers and laptops in transit.
Which government filings change when a Georgia office moves?
A Georgia office move usually means four address updates:
-
USPS: file one Business Move request for the whole company. In person, USPS wants proof you can act for the business.
-
IRS: send Form 8822-B for a new mailing address or location. The form says processing generally takes 4 to 6 weeks.
-
Georgia Secretary of State: change the entity address by filing an annual registration, or an amended one ($30) if this period’s is already filed.
-
City of Atlanta: tell the Business Tax Division as soon as possible. A move within city limits needs zoning approval, with a $50 review fee. Outside Atlanta, ask your city or county.
Common questions
How far in advance should an office move be planned?
Eight weeks or more. Building paperwork (COI, dock, freight elevator) and the internet circuit at the new suite are the two lead times that cannot be compressed.
Do office moves have to happen after hours?
Many managed Atlanta office buildings require moves outside business hours — evenings or weekends — so check both buildings’ rules.
Who packs the desks in an office move?
Employees pack their own desks into labeled boxes with a deadline the day before; movers or a packing crew handle common areas, equipment, and furniture teardown.